Vaughan Civil was integral in the delivery of the project by expediting sections of works and maximising resources on site to meet the critical timeline of the project.
Vaughan Civil was integral in the delivery of the project by expediting sections of works and maximising resources on site to meet the critical timeline of the project.
Vaughan Civil are carrying out upgrade works to the existing Beenleigh Wastewater Treatment Plant (WWTP) to boost capacity to the local network, enhance environmental performance, and reduce operational costs. The project will see a brand-new wastewater pump station, 2km of DN800 rising main pipeline, integrated shutdowns within the existing plant during commissioning and associated infrastructure… Continue reading Beenleigh Wastewater Treatment Plant Upgrade
The Design and Construction (D&C) of 28km of pipeline and construction of 3 water pumping stations, as part of a water security program for Mount Morgan, near Rockhampton QLD. The development will future-proof the supply of long-term quality drinking water for Mount Morgan and surrounding areas. Scope of works includes: The D&C of all 3… Continue reading Mount Morgan Water Supply Project – Pipeline & Pumpstations
Ausgrid’s CONSAC Replacement Project has set out to progressively replace the existing underground low voltage electricity cables in the Sydney area. These cables are reaching the end of their serviceable life and are being replaced to allow Ausgrid to maintain a safe and reliable electricity network. Vaughan Civil were awarded the Design and Construct contract… Continue reading Illawong & Menai CONSAC Replacement Project
The Aerotropolis 132kV Feeder Stage 3B serves as a critical infrastructure project to fuel the Western Sydney’s long-term expansion and energy needs.
The Moorebank Interstate Terminal Development and Rail Access project is a nationally significant infrastructure development that will transform the way containerised freight moves through Sydney and along the east coast.
Vaughan Civil was the primary contractor for the Liverpool CBD Sewer Trunk upgrade which included DN1800 manholes and pipes varying from DN300 to DN150. Our scope is includes: 250m trenching for 300mm, 225mm and 150mm PVC Sewer Pipe 250m of Under boring of 457OD Steel Casing for 300mm PVC Sewer pipe Construction of 6 x… Continue reading Liverpool CBD Sewer Upgrade
Vaughan Civil were awarded the principal contract for the Prospect to MacArthur (ProMac) works. ProMac will help Sydney Water deliver on its vision of creating a better life with world-class water services.
As part of the Prospect to Macarthur (ProMac) project, Vaughan Civil carried out the construction a new water pumping station in Harrington Park, to provide drinking water services for 84,000 new homes in the Southwest Growth Area and Western Sydney Aerotropolis Growth Area. This pump station helped bolster the water transfer link from Prospect South… Continue reading Harrington Park Water Booster Pump Station
Vaughan Civil were awarded the CMW Tunneling package (electrical scope). The Sydney Metro West Project – Central Tunneling Package comprises twin 6m diameter TBM tunnels running approximately 11km from the launch shaft at The Bays to the retrieval shaft at Sydney Olympic Park.